| | | Date | 05-16-2020 | | Pass-On Subject | C-shift Pass On | | Pass-On Information | -HM20 weekly completed. 3 SCBA had dead HUD batteries and were replaced. Batteries removed from voice amps and placed in battery box to avoid corrosion. Batteries removed from Draeger CMS unit and left in box. All Draeger tubes consolidated into 1 case. Empty meter case removed as well. -Level B suit inventory changed. Encapsulating B suits removed. 6 flash protection suits added. 4XL suits reduced to a total of 3, 4 XL Tychem CPF3 suits added. Bags for all suits clearly labeled. -Boats were checked in preparation for the potential TS. Please run the motor each morning. Its been slow to start. | | Name | Olson / Fraley | | Email | dolson@washco-md.net |
| | | | | |
|