Wednesday, May 22, 2019

Pass-On

 
 
  Pass-On
 
Date 05-22-2019
Pass-On Subject 5-22-19
Pass-On Information • Boat trailer lights OOS.  BS20 dash indicates trailer-wiring fault.
• Training on BT20 at dam 3 ruins.  No issues and no damage incurred.  BS20 & BT20 fueled.
• Supp203 weekly completed by J. Hart.  Oil low 1qt (added), drivers side scene light has arcs when moved, no emergency lights on body.
• Bay floor weekly will be completed Sunday due to crew being on river all day.


Incidents:
19-11448 // 134 Ross St // House Fire
Name Dave Olson
Email enginedriver71@comcast.net
 
     
 
 

Re: Apparatus Maintenance Request - Jon Hart

 
  Apparatus Maintenance Request
 
Name Jon Hart
Date 05-22-2019
Email jhart@washco-md.net
Unit SUP203
Unit Status In Service
Description of Issue The driver side pole/scene light is not working; it arcs  when it comes in contact with the bed body.
The side LED emergency flashers are not working.
The parking brake is not working.
 
     
 
 

Friday, May 17, 2019

Pass-On

 
 
  Pass-On
 
Date 05-16-2019
Pass-On Subject A-Crew
Pass-On Information - Apparatus checked
- SCBA's checked
- yard mowed and bailed
- station choirs complete
- training 0900-1130
- bagged up 2000 of the red ready kits
     * distributed them to station reps at
        the association meeting at E-5.

**NO CALLS**
Name Keith Hose
Email Khose@washco-md.net
 
     
 
 

Monday, May 13, 2019

Pass-On

 
 
  Pass-On
 
Date 05-12-2019
Pass-On Subject A-crew
Pass-On Information Hose detailed to EMT-refresher 8-2.
Shealy(daylight)/Poffinberger
Station choirs completed
Squad 20-01 checked
- did not wash with the rainy weather.
No calls
Worked on new decals for the Chesapeake, ordering those soon.

Name Keith Hose
Email Khose@washco-md.net
 
     
 
 

Sunday, May 12, 2019

EDIT: Pass-On

 
 
  Pass-On
 
Date 05-10-2019
Pass-On Subject C-Shift
Pass-On Information •  18 4x4s placed on collapse trailer.  
•  Engulfment cofferdam equipment removed from collapse trailer and placed on pallet and placed behind small squad.
•  (2) header/sole sets premade to 4' and placed in collapse trailer w/ wedge packs attached.  Stored in rear with wallers.
•  (1) Paslode gun OOS.  Would not fire.
•  Extra 4x4 lumber placed on rack behind hazmat unit.
Name David Olson
Email EngineDriver71@comcast.net
Upload Photo Header-Sole Setup.jpg
 
     
 
 

Friday, May 10, 2019

Pass-On

 
 
  Pass-On
 
Date 05-10-2019
Pass-On Subject C-Shift
Pass-On Information •  18 4x4s placed on collapse trailer.  
•  Engulfment cofferdam equipment removed from collapse trailer and placed on pallet and placed behind small squad.
•  (2) header/sole sets premade to 4' and placed in collapse trailer w/ wedge packs attached.  Stored in rear with wallers.
•  (1) Paslode gun OOS.  Would not fire.
•  Extra 4x4 lumber place don rack behind hazmat unit.
Name David Olson
Email EngineDriver71@comcast.net
Upload Photo Header-Sole Setup.jpg
 
     
 
 

Thursday, May 9, 2019

Pass-On

 
 
  Pass-On
 
Date 05-08-2019
Pass-On Subject A- shift
Pass-On Information UT- 203 checked

BS-20 fueled

Squad 20 Fueled

Ordered (30) 4x4x10 non-treated, kiln     dried southern yellow pine. It will be ready for pickup at Carter lumber on 5/9.

Training competed

Taught Hazmat refresher at Wash. Co. Sheriff's Dept. for Fire Police.

Boat 20 was requested to return too Knob Rd to assist in a continued search operation. Approved by Hart.



Name Keith Hose
Email Khose@washco-md.net